造價員《工程計量與計價實(shí)務(wù)》模擬試題(四)計算題
三、計算題
某工業(yè)廠房±0.00~3.27m結(jié)構(gòu)圖如圖所示,柱、剪力墻砼為C35,梁、板砼為C30,柱和剪力墻底標(biāo)高-2.5M(基礎(chǔ)頂面標(biāo)高),室外設(shè)計標(biāo)高-0.3M,板厚均為120mm.請按江蘇省04計價表計算:
1、柱、梁、板、剪力墻砼工程量。
2、按接觸面積計算KZ1、KZ2柱和梁、板模板工程量。
3、對計算出的以上工程量套用計價表子目并計算綜合單價。(π取值3.14;柱、剪力墻砼工程量從基礎(chǔ)頂面標(biāo)高起算;柱模板工程量從基礎(chǔ)頂面標(biāo)高起算;施工時柱分兩次澆筑;砼采用商品砼泵送;模板施工采用復(fù)合木模板;小數(shù)點(diǎn)后保留兩位小數(shù)。)
【建設(shè)工程教育網(wǎng)答案解析】
?。ㄒ唬┯媰r表工程量計算表
序號 |
項(xiàng)目 |
計算公式 |
計量單位 |
數(shù)量 |
1 | 柱砼 | KZ1:0.65×0.6×(2.5+3.27-0.12)×4 | m3 | 8.81 |
KZ2:0.65×0.7×(2.5+3.27-0.12)×4 | m3 | 10.28 | ||
小計 | m3 | 19.09 | ||
2 | 剪力墻砼 | [(15.6+3.6×2+3.45×2+0.45×4)×(2.5+3.27-0.12)-1.8×0.9×2-3.14×0.42-0.9×2.1×2] ×0.3+(3.6+5.1)×0.3×0.12 | m3 | 51.45 |
3 | 梁砼 | KL1:0.3×0.58×(8+7.2-0.5-0.65-0.15)×4 | m3 | 9.67 |
KL2:0.3×0.58×(6.9×2+1.8-0.45×2-0.6×2) | m3 | 2.35 | ||
KL3:0.25×0.48×(6.9×2+1.8-0.55×2-0.7×2) | m3 | 1.57 | ||
KL4:0.3×0.48×(6.9×2+1.8-0.45×2-0.6×2) | m3 | 1.94 | ||
L1: 0.3×0.43×(7.2-0.15-0.125) | m3 | 0.89 | ||
L2: 0.25×0.33×(6.9-1.8-0.15×2) | m3 | 0.40 | ||
小計 | 16.82 | |||
4 | 板砼 | [(15.6+0.3)×(8+7.2+0.3)+(6.9+1.8+1.5+0.3)×3.6] ×0.12 | m3 | 34.11 |
5 | 柱模板 | KZ1:(0.65+0.6)×2×(2.5+3.27-0.12)×4 扣梁頭0.3×0.58×10個=-1.74 |
m2 | 54.76 |
KZ2:(0.65+0.7)×2×(2.5+3.27-0.12)×4 扣梁頭0.3×0.58×8+0.25×0.48×6=-2.11 扣梁頭 |
m2 | 58.91 | ||
小計 | m2 | 113.67 | ||
6 | 梁、板模板 | 方法一:梁底模在板中算 (15.6+0.3)×(8+7.2+0.3)+(6.9+1.8+1.5+0.3)×3.6=284.25 扣柱頂:0.65×0.6×4+0.65×0.7×4=-3.38 扣剪力墻頂:(0.6+3.45×3+0.45×3+10.5)×0.3=-6.84 梁側(cè): KL1: 0.58×2×(8+7.2-0.5-0.65-0.15)×4=64.5 KL2: 0.58×2×(6.9×2+1.8-0.45×2-0.6×2)=15.66 KL3: 0.48×2×(6.9×2+1.8-0.55×2-0.7×2)=12.58 KL4: 0.48×2×(6.9×2+1.8-0.45×2-0.6×2)=12.96 L1: 0.43×2×(7.2-0.15-0.125)=5.96 L2: 0.33×2×(6.9-1.8-0.15×2)=3.17 扣梁頭:0.3×0.43×2+0.25×0.33×2+0.25×0.28=-0.49 板側(cè):(15.9+19.1+10.5+4.85+15.5)×0.12=7.90 方法二:梁底模在梁中算 梁模板: KL1: (0.58×2+0.3)×(8+7.2-0.5-0.65-0.15)×4=81.18 KL2: (0.58×2+0.3)×(6.9×2+1.8-0.45×2-0.6×2)=19.71 KL3: (0.48×2+0.25)×(6.9×2+1.8-0.55×2-0.7×2)=15.85 KL4: (0.48×2+0.3)×(6.9×2+1.8-0.45×2-0.6×2)=17.01 L1: (0.43×2+0.3)×(7.2-0.15-0.125)=8.03 L2: (0.33×2+0.25)×(6.9-1.8-0.15×2)=4.37 小計:146.15 板底模: LB1:(8-0.15-0.125)×(6.9-0.3)-0.35×0.3×2-0.4×0.175×2=50.64 LB2:(8-0.15-0.125)×(1.8-0.3)=11.59 LB3:同LB1 50.64 LB4:(3-0.125×2)×(6.9-1.8-0.3)-0.4×0.175=13.13 LB5:(4.2-0.15-0.125)×(6.9-1.8-0.3)=18.84 LB6:(7.2-0.15-0.125)×(1.8-0.3)-0.4×0.175=10.32 LB7:(7.2-0.15-0.125)×(1.8-0.3)=10.39 LB8:(7.2-0.15-0.125)×(6.9-0.3)-0.4×0.175×2=45.57 LB9:1.5×(3.6-0.3)=4.95 LB10:(1.8-0.3)×(3.6-0.3)=4.95 LB11:(3.6-0.3)×(6.9-0.3)=21.78 小計:242.8(3) 扣梁頭:0.3×0.43×2+0.25×0.33×2+0.25×0.28=-0.49 板側(cè):(15.9+19.1+10.5+4.85+15.5)×0.12=7.90 |
m2 | |
小計 | m2 | 396.27 (396.36) |
?。ǘ┨子糜媰r表子目綜合單價計算表
計價表編號 | 子目名稱 | 單位 | 數(shù)量 | 綜合單價(列簡要計算過程)(元) | 合價(元) |
5-181換 | 矩形柱 | m3 | 19.09 | 351.15-293.04+0.99×306=361.05 | 6892.44 |
5-193換 | 直形墻 | m3 | 51.45 | 347.03-293.63+0.992×306=356.95 | 18365.08 |
5-199 | 有梁板 | m3 | 50.93 | 348.25 | 17736.37 |
20-26 | 柱模板 | 10m2 | 11.37 | 212.85 | 2420.10 |
20-59 | 現(xiàn)澆板模板 | 10m2 | 39.63 (39.64) |
208.97 | 8281.48 (8283.57) |
- · 造價員《工程計量與計價實(shí)務(wù)》模擬試題(四)計算題
- · 造價員《工程計量與計價實(shí)務(wù)》模擬試題(四)計算題
- · 造價員《工程計量與計價實(shí)務(wù)》模擬試題(四)多選1-10題
- · 造價員《工程計量與計價實(shí)務(wù)》模擬試題(四)多選1-10題
- · 造價員《工程計量與計價實(shí)務(wù)》模擬試題(四)11-20題
- · 造價員《工程計量與計價實(shí)務(wù)》模擬試題(四)11-20題
- · 造價員《工程計量與計價實(shí)務(wù)》模擬試題(四)1-10題
- · 造價員《工程計量與計價實(shí)務(wù)》模擬試題(四)1-10題